  • Price depends on size, thickness, finish, site prep, and access. Every quote is free and based on your actual site.

  • Start with what you see. Find it in our problem list, or describe it in your quote request and we'll tell you what it needs.

  • Yes. The same crew handles every stage, from excavation to the final finish.

  • Joliet and the Greater Chicagoland area.

  • We work 7 days a week, which gives more room to find a day that works for you.

  • Slabs, parking lots, curb and gutter, and foundations, across Joliet and the Greater Chicagoland area.

Permits & planning

  • In Joliet, yes for driveways, aprons, sidewalks, patios with or without a roof, garages, and additions. Replacing a driveway, apron, or sidewalk at the same size needs one too. Other towns set their own rules.

  • It's the surveyed drawing of your property. For a Joliet permit, the new work gets marked on it, and the city's Planning Division reviews its location and size.

  • Whoever does the digging. Illinois law requires them to notify JULIE at least 3 days ahead, not the homeowner or the company the work is for.

    Source: JULIE

  • No. Utilities only mark the lines they own. Private lines like sprinklers, private lighting, sewer and septic lines, pools, and power to a detached garage aren't marked, so point them out before the dig.

    Source: JULIE

  • Yes. Every new garage needs an approved concrete foundation and a permit with an accurate plat of survey.

  • After the footings are dug and before they're poured, and again before the foundation walls are poured.

  • Under the ISPSC, which many Illinois towns adopt:

    • Barriers are at least 48 in. high.
    • Gates are self-closing and self-latching, and open away from the pool.
    • The gap under a barrier on a solid surface is no more than 4 in.
    • A 36 in. clear zone keeps climbable objects away from the barrier.

    Check your town's adopted code, and plan the deck and barrier together.

Cracks, curing & care

Driveways, patios & stamped

Excavation

  • In Joliet, installing or replacing a driveway, apron, sidewalk, or patio needs a permit with a plat of survey, even at the same size and spot. Other towns set their own rules.

  • A slab is only as good as what it sits on. Soft spots are dug out and replaced with compacted gravel or crushed rock, so the slab sits on an even base and doesn't settle unevenly.

Floors & foundations

Commercial, lots & curb

  • New concrete reflects about 40% of sunlight and new asphalt about 5%. The gap narrows with age: concrete may reach about 25% after 5 years, and asphalt about 20% after seven.

    Source: U.S. EPA

  • ACI 330 guidance puts standard car lots at about 5 in. and truck areas at about 6.5 in.

    Source: PACA

  • When the lot is jointed into short panels, ACI 330 says distributed steel isn't necessary, and dowels aren't needed for most parking lots.

  • About 10–12 ft on a 5 in. slab, and about 15 ft on an 8 in. slab.

    Source: PACA

  • Illinois sets it by the total number of off-street spaces:

    • 1 to 25: 1
    • 26 to 50: 2
    • 51 to 75: 3
    • 76 to 100: 4
    • 101 to 150: 5
    • 151 to 200: 6
    • 201 to 300: 7
    • 301 to 400: 8
    • 401 to 500: 9
    • 501 to 1,000: 2% of total
    • Over 1,000: 20, plus 1 for each 100 over 1,000
    • Hospital outpatient facilities: 10% of total
    • Rehabilitation and physical therapy: 20% of total
  • 16 ft wide for off-street spaces, including a diagonally striped access aisle 8 ft or 5 ft wide.

  • Federal ADA standards allow no more than 1:48 in any direction for spaces and their aisles, and Illinois' accessibility code applies as well.

  • It's IDOT's shorthand. B means barrier, a curb with a vertical face. The 6 is the curb height in inches, and the 12 is the gutter width in inches.

    Source: IDOT manual

  • A barrier curb has a vertical face, and a mountable curb has a sloping one. On streets designed for 45 mph or less, either can be used, so your plans or your town's detail decide.

    Source: IDOT manual

  • Under IDOT's standard, contraction joints match the adjacent concrete pavement, never more than 15 ft apart. They're sawed 2 in. deep 4 to 24 hours after the pour, then sealed.

  • Under Will County's subdivision rules, it's required in every nonresidential subdivision, in residential ones where lots average less than 120 ft wide at the front, and where slopes exceed 5%. The required type is B-6.12.

Close-up of a finished stamped concrete surface

Get started

Ask us directly.

Call 815-836-1828, 7 days a week, or request a free quote and we'll answer it at the visit.

Free quotes, 7 days a week.

Serving Greater Chicagoland

7 days a week